Modular Construction Large Projects Netherlands
Facts & Figures

300.000

170.000

2023:

per year

Growing to

vs. 2022

+60%

Heat pump installation

2 million

500 charging stations a day

That's an average of

in 2030

Growing to

500.000

2023:

charging stations

Charging stations

The rest is for industry, businesses,
data centres, residential areas,
hydrogen plants

75 GW

Amsterdam)

the power of

Over

150x

105

gigawatt

Requesting an increase or new connection 2023

is large-scale battery power

Of that,

streets have to be opened for laying new cables from grid operators

1 in 3

€8 billion

a year

that grows to:

Until 2025,

€5 billion

by 2023

Over

Investments grid operators

existing high-voltage substations

(110 - 150kV)

Conversion and extension of

Construction of

locations, TenneT has to construct

700

In over

high-voltage pylons

1.000

Construction of

of transmission line

Construction of many kilometers of underground connections (110 en 150 kV)

140

Portfolio TenneT
increase x 10

350 km

Construction of

380 kV substations

new

14

faster

Development and construction of high-voltage substations:

0,5 to 2 years

faster

Development and construction of high-voltage pylons:

Shorter lead times to be expected with modular construction

0,5 to 4 years

Together with shortening lead times for RCR procedures, one of the other smart solutions, we can achieve even shorter lead times.

Future

Current

10 -30%

Construction of the project

Realisation phase

20 -70%

Engineering

Design phase

5-20%

Failures, replacement, maintenance of components

Maintenance and controlling phase

10 -40%

Work order of executing parties, ordering materials, suppliers

Preparation and execution phase

Expected savings with modular construction

20 -40%

Participation, permits (land purchase), soil investigation

Planning phase

Interchangeability of materials, stock management, less specialisation and also interchangeability of technically skilled personnel. Every substation is the same.

5-20%

Failures, replacement, maintenance of components

Maintenance and controlling phase

Unified working method, greater flexibility, substitutability of materials.

10 -30%

Construction of the project

Realisation phase

Basically, everything is fixed. As a result, working with prefab components, materials in stock, repetitive work, unambiguous work instructions, more efficient work.

10 -40%

Work order of executing parties, ordering materials, suppliers

Preparation and execution phase

30-80% of the design is ready. Only site-specific designs are still needed.

20 -70%

Engineering

Design phase

Expected savings with modular construction

20 -40%

At early stage, impact on surroundings is known. Frameworks are immediately clear, which can help in discussions with surroundings.

Participation, permits (land purchase), soil investigation

Planning phase

Together with shortening lead times for RCR procedures, one of the other smart solutions, we can achieve even shorter lead times.

Future

Current

faster

Development and construction of high-voltage substations:

0,5 to 2 years

faster

Development and construction of high-voltage pylons:

Shorter lead times to be expected with modular construction

0,5 to 4 years

existing high-voltage substations

(110 - 150kV)

Conversion and extension of

Construction of

locations, TenneT has to construct

700

In over

high-voltage pylons

1.000

Construction of

of transmission line

Construction of many kilometers of underground connections (110 en 150 kV)

140

Portfolio TenneT
increase x 10

350 km

Construction of

380 kV substations

new

14

1 in 3

streets have to be opened for laying new cables from grid operators

€8 billion

a year

that grows to:

Until 2025,

€5 billion

by 2023

Over

Investments grid operators

The rest is for industry, businesses,
data centres, residential areas,
hydrogen plants

105

gigawatt

the power of

van Amsterdam)

150x

Over

is large-scale battery power

Of that,

75 GW

Requesting an increase or new connection 2023

2 miljoen

500 charging stations a day

That's an average of

in 2030

Growing to

charging stations

500.000

2023:

Charging stations

300.000

170.000

2023:

per year

Growing to

vs. 2022

+60%

Heat pump installation
Facts & Figures
Modular Construction Large Projects Netherlands

TenneT Magazines

TenneT would like to get in touch with you. Below you will find an overview of our online magazines on important topics and programmes.
Fullscreen